Overview
The short answer, phase by phase, per 1,000 square feet
Start with the unit we plan around: 1,000 square feet of open, rectangular space. Day one is removal — the old carpet, vinyl, laminate, or tile comes up, tack strips and staples come out, and the debris leaves the house. Carpet and floating floors come up fast; glued-down material and ceramic tile are slower and louder, and tile demolition alone can fill the whole first day on a 1,000-square-foot area. Nothing new goes down on day one, which surprises homeowners who expected installation to start immediately — but every hour saved by rushing removal gets paid back in prep problems later.
Day two is preparation, and it is the phase that decides how the floor performs. On Jacksonville's concrete slabs we run a moisture test before anything is installed, because a slab that is still releasing moisture will defeat adhesives and can telegraph problems through a new floor. High spots get ground down, low spots get leveling compound that needs its own drying time, and any cracked or soft sections get repaired. On wood subfloors in older Mandarin, Southside, and Orange Park homes, prep means checking for squeaks, rot around kitchens and baths, and sections that need to be cut out and replaced. Skipping prep is how a floor ends up hollow-sounding, uneven at the seams, or failing early.
Installation is the phase homeowners picture: for click-lock luxury vinyl plank, an experienced crew typically covers 300 to 500 square feet a day in real rooms — less in cut-up layouts with hallways, closets, and stairs, more in open great rooms common in Nocatee and St. Johns builds. Tile installs slower and in forced stages: setting one day, grouting only after the thinset has cured, then a further cure before heavy furniture returns. The last phase is trim — baseboards, quarter round, and transition strips at every doorway — plus a walkthrough. Trim is usually half a day to a full day per 1,000 square feet, and it is what makes the job look finished instead of almost finished.
So the realistic totals, per 1,000 square feet: vinyl plank runs about three to five working days start to finish, and most homeowners can walk on it in socks the same evening it goes down. Tile runs about five to eight working days because of cure times, and large whole-home jobs scale by area and by how cut-up the floor plan is — a 2,000-square-foot whole-home plank job is usually a week to a week and a half, not simply double, because removal and trim get more efficient at scale while prep findings decide the rest. At the estimate we confirm which rooms, which material, and which phases apply to your home, and we put the expected day count in writing.